The ILP was established by FERC regulations (18 C.F.R. Part 5) on July 23, 2003. The ILP provides for increased public participation and consultation prior to filing the relicensing application. Learn more about the ILP, including a process timetable at www.ferc.gov/industries/hydropower/gen-info/licensing/ilp.asp.

DateProject Milestones
2003Relicensing background data collection begins
Jan-2004Georgia Power files Preliminary Application Document (PAD)
Apr-2004FERC Scoping Meetings & Site Visit
Jun-2004Georgia Power files Study Plan with FERC
Jul-2004Study Plan Meetings
2004 - 2005Georgia Power conducts studies in resource areas
Nov-2005Georgia Power files Study Plan Progress Report
Apr-2006Georgia Power files Final Study Reports
Study Report Meetings with Stakeholders
Oct-2006Georgia Power files licensing proposal
Feb-2007Georgia Power files License Application