Plant McDonough-Atkinson

Plant McDonough-Atkinson began commercial operation in 1941 in Cobb County, Georgia and retired its coal-fired units in 2011 and 2012. Three natural gas combined cycle units, capable of producing 2,520 MW of electricity, then began commercial operation in 2012.

Ash Pond Dewatering Plan

Georgia Power prepares and submits an ash pond dewatering plan to the Georgia Environmental Protection Division for its approval. This site-specific plan identifies the enhanced water treatment system, controls and monitoring that will be used during the closure process to ensure that the water discharged is fully protective of a receiving stream's water quality.

Ash Pond Dewatering Results

Discharged water is being actively sampled in compliance with federal and state regulations. Data results will be updated as the process continues.


CCR Rule Compliance Data and Information

Georgia Power submitted CCR permit applications to the Georgia Environmental Protection Division in November 2018. The documents provided herein represent the approved permit(s) or current submittals as of May 2023 still under EPD review and the link to the final EPD approved CCR permit and documents will be provided upon permit issuance.


AP-1

Groundwater

Assessment of Corrective Measures

Notice of Assessment of Corrective Measures - July 2020

Assessment of Corrective Measures Report

Draft Remedy Selection Report – August 2023

 

Ongoing semiannual updates to the site Assessment of Corrective Measures are provided as part of the Groundwater Monitoring and Corrective Action Reports


AP-2

Groundwater

Assessment of Corrective Measures

Notice of Assessment of Corrective Measures - July 2020

Assessment of Corrective Measures Report

Draft Remedy Selection Report – August 2023

 

Ongoing semiannual updates to the site Assessment of Corrective Measures are provided as part of the Groundwater Monitoring and Corrective Action Reports


AP-3

Groundwater

Assessment of Corrective Measures

Notice of Assessment of Corrective Measures - July 2020

Assessment of Corrective Measures Report

Draft Remedy Selection Report – August 2023

 

Ongoing semiannual updates to the site Assessment of Corrective Measures are provided as part of the Groundwater Monitoring and Corrective Action Reports


AP-4

Groundwater

Assessment of Corrective Measures

Notice of Assessment of Corrective Measures - July 2020

Assessment of Corrective Measures Report

Draft Remedy Selection Report – August 2023

 

Ongoing semiannual updates to the site Assessment of Corrective Measures are provided as part of the Groundwater Monitoring and Corrective Action Reports

Additional information will be provided as it becomes available or as it is required.