Plant McManus began commercial operation in the 1950s in Glynn County, Georgia and the two steam units were retired in 2015. The remaining nine oil-fired combustion turbines are capable of producing 480 MW of electricity.
The company prepares and submits an ash pond dewatering plan to the Georgia Environmental Protection Division for its approval. This site-specific plan identifies the enhanced water treatment system, controls and monitoring that will be used during the closure process to ensure that the water discharged is fully protective of a receiving stream's water quality.
Discharged water is being actively sampled in compliance with federal and state regulations. Data results will be updated as the process continues.
CCR Permit documents provided herein represent the approved permit(s) and permit documents or current submittals to EPD as of January 2025. Once a CCR Permit is issued, modifications to the permit documents will be updated on this website as they are approved by the EPD.
The CCR solid waste permit has been issued for AP-1. Please refer to the permit and supporting documents which reflect the approved plans for the site.
Annual Fugitive Dust Control Report - 2018
Annual Fugitive Dust Control Report - 2018 Addendum
Annual Fugitive Dust Control Report - 2019
Annual Fugitive Dust Control Report - 2020
Annual Fugitive Dust Control Report - 2021
Annual Fugitive Dust Control Report - 2022
Appendix IV SSL Notification - May 2020
Appendix IV SSL Notification - August 2020
Appendix IV SSL Notification – January 2021
Appendix IV SSL Notification – July 2021
Appendix IV SSL Notification – January 2022
Appendix IV SSL Notification – July 2022
Appendix IV SSL Notification – January 2023
Appendix IV SSL Notification – July 2023
Annual Groundwater Monitoring and Corrective Action Report - 2019
Semi-Annual Groundwater Monitoring and Corrective Action Report - 2019
Annual Groundwater Monitoring and Corrective Action Report - 2020
Semi-Annual Groundwater Monitoring and Corrective Action Report – 2020
Annual Groundwater Monitoring and Corrective Action Report – 2021
Semi-Annual Groundwater Monitoring and Corrective Action Report – 2021
Annual Groundwater Monitoring and Corrective Action Report – 2022
Semi-Annual Groundwater Monitoring and Corrective Action Report – 2022
Annual Groundwater Monitoring and Corrective Action Report – 2023
Semi-Annual Groundwater Monitoring and Corrective Action Report – 2023
Annual Groundwater Monitoring and Corrective Action Report – 2024
Notice of Assessment of Corrective Measures - July 2020
Assessment of Corrective Measures Report
Draft Remedy Selection Report – January 2024
Ongoing semiannual updates to the site Assessment of Corrective Measures are provided as part of the Groundwater Monitoring and Corrective Action Reports
Additional information will be provided as it becomes available or as it is required.