Plant Yates

Plant Yates began commercial operation in 1950 in Coweta County, Georgia, and five of the seven coal-fired units were retired in 2015. The two remaining units, capable of producing 700 MW of electricity, were converted to natural gas.

Ash Pond Dewatering Plan

The company prepares and submits an ash pond dewatering plan to the Georgia Environmental Protection Division for its approval. The ash pond dewatering plan for Plant Yates was approved by EPD in September 2018. This site-specific plan identifies the enhanced water treatment system, controls and monitoring that will be used during the closure process to ensure that the water discharged is fully protective of a receiving stream's water quality.

Ash Pond Dewatering Results

Discharged water is being actively sampled in compliance with federal and state regulations. Data results will be updated as the process continues.

CCR Rule Compliance Data and Information

CCR Permit documents provided herein represent the approved permit(s) and permit documents or current submittals to EPD as of January 2025. Once a CCR Permit is issued, modifications to the permit documents will be updated on this website as they are approved by the EPD.


AP-A

Design Criteria

Operating Criteria

Closure & Post Closure Care

Groundwater

Assessment of Corrective Measures

Notice of Assessment of Corrective Measures - June 2019

Assessment of Corrective Measures Report - 2019

Semi-Annual Remedy Selection and Design Progress Report

Draft Remedy Selection Report – September 2024

 

Ongoing semiannual updates to the site Assessment of Corrective Measures are provided as part of the Groundwater Monitoring and Corrective Action Reports

Location Restriction Demonstration


AP-B

Design Criteria

Operating Criteria

Closure & Post Closure Care

Groundwater

Assessment of Corrective Measures

Notice of Assessment of Corrective Measures - February 2019

Assessment of Corrective Measures Report - 2019

Semi-Annual Remedy Selection and Design Progress Report

Draft Remedy Selection Report – September 2024

 

Ongoing semiannual updates to the site Assessment of Corrective Measures are provided as part of the Groundwater Monitoring and Corrective Action Reports

Location Restriction Demonstration


AP-B'

Design Criteria

Operating Criteria

Closure & Post Closure Care

Groundwater

Assessment of Corrective Measures

Notice of Assessment of Corrective Measures - February 2019

Assessment of Corrective Measures Report - 2019

Semi-Annual Remedy Selection and Design Progress Report

Draft Remedy Selection Report – September 2024

 

Ongoing semiannual updates to the site Assessment of Corrective Measures are provided as part of the Groundwater Monitoring and Corrective Action Reports

Location Restriction Demonstration


AP-1

The CCR solid waste permit has been issued for AP-1. Please refer to the permit and supporting documents which reflect the approved plans for the site.

Design Criteria

Operating Criteria

Closure & Post Closure Care

Groundwater

Location Restriction Demonstration


AP-2

The CCR solid waste permit has been issued for AP-2. Please refer to the permit and supporting documents which reflect the approved plans for the site.

Design Criteria

Operating Criteria

Closure & Post Closure Care

Groundwater

Location Restriction Demonstration


AP-3

Design Criteria

Operating Criteria

Closure & Post Closure Care

Groundwater

Assessment of Corrective Measures

Notice of Assessment of Corrective Measures - February 2019

Assessment of Corrective Measures Report - 2019

Semi-Annual Remedy Selection and Design Progress Report

Draft Remedy Selection Report – September 2024

 

Ongoing semiannual updates to the site Assessment of Corrective Measures are provided as part of the Groundwater Monitoring and Corrective Action Reports

Location Restriction Demonstration


R6 Landfill and AP-C


Gypsum Stack Landfill

On November 25, 2024, EPD issued a Release from CCR Handling Permit for the Yates Gypsum Stack Landfill. All obligations for the Closure by Removal have been met. This officially designates the facility as closed and released from the CCR Permit.

Groundwater

Additional information will be provided as it becomes available or as it is required.